What happens each day

Bath_Express_Logo_L_NO_TXT.jpg

wh1.JPG

Beginning of day 1, the before picture

wh2.JPG

End of day 1, demolition completed
 
 
 
 
 

wh3.JPG

End of Day 2, plumbing, tub and valves are in.
 
 
 
 
 

wh4.JPG

End of Day 3, electrical re-wiring done.
 
 
 
 
 

Days 4 and 5 left open for Town inspections.
   (no further work allowed until inspections passed).
 
 
 
 
 

wh5.JPG

End of Day 6, insulation completed.
 
 
 
 
 

wh6.JPG

wh7.JPG

End of Day 7, sheetrock and cement-board in shower installed.
 
 
 
 
 

wh8.JPG

End of Day 8, window and door trim go up, and 2nd coat of taping to smooth walls.
 
 
 
 
 

wh9.JPG

End of Day 9, tile installed.
 
 
 
 
 

wh10.JPG

End of Day 10, tile is grouted, mirror frame installed.
 
 
 
 
 

wh11.JPG

End of Day 11, final prep work before painting.
 
 
 
 
 
 
 

wh12.JPG

End of Day 12, painting done, cabinets installed.
 
 
 
 
 

wh13.JPG

End of Day 13, towel bars, t.p. paper holders, etc. installed.
 
 
 
 
 
 

wh14.JPG

End of Day 14, counter, faucets and lights installed.
Bathroom finished!
 
 
 
Day 15.  Available if needed.